Adani Green Energy's 1,500 MW pumped storage project on the Tarali dam reservoir in Maharashtra's Satara district is at the centre of a row over its declared cost. A company affidavit cut the…

Explained: Adani Tarali Project Cost Row and Wildlife Fee
The Tarali pumped storage project site in Satara district, Maharashtra. The project cost row has led to a halt on construction work at the site.

Adani Green Energy's 1,500 MW pumped storage project on the Tarali dam reservoir in Maharashtra's Satara district is at the centre of a row over its declared cost. A company affidavit cut the project cost from Rs 5,675 crore to Rs 56.75 crore, cutting the wildlife conservation deposit it had to pay from Rs 227 crore to Rs 2.27 crore. Work at the site has now been stopped, by the forest department and the pollution control board, while a Centre-ordered inquiry is under way.

What is the Tarali project

The Tarali project is a 1,500 MW Pumped Storage Project, proposed on the Tarali dam reservoir. In such a project, water is pumped to an upper reservoir when power is plentiful and released downhill through turbines to generate electricity when demand peaks.

The project is being developed by Adani Green Energy Ltd, the renewable energy company of the Adani Group, on 150.74 hectares of non-forest land in Nivade, Tondoshi, Kalambe and Jalu villages in Patan taluka of Maharashtra's Satara district.

Why was the company asked to pay Rs 227 crore

A letter from the Union Ministry of Environment, Forest and Climate Change on February 11, 2025, recommending prior Environment Clearance for the project, mentioned the project cost as Rs 5,675 crore.

The state forest department says the project falls within the deemed Eco-Sensitive Zone of the Koyna Wildlife Sanctuary in Satara, part of the Sahyadri Tiger Reserve. Under existing norms, private companies setting up projects in such a zone can be asked to deposit up to 4 percent of the project cost towards conservation and protection.

At its meeting on February 23, 2026, the State Board for Wildlife laid down 15 conditions for the project, one of which required 4 percent of the project cost to be deposited in the Sahyadri Tiger Reserve's bank account.

In a letter dated March 24, 2026, Principal Chief Conservator of Forests (Wildlife) M Shrinivas Reddy asked the company to deposit Rs 227 crore into the Sahyadri Tiger Reserve Conservation Foundation and submit an affidavit confirming it would fulfil the other 14 conditions, after which the proposal would go to the National Board for Wildlife. A follow-up letter from the Deputy Director of Koyna Wildlife Sanctuary on May 7, 2026, reiterated the Rs 227 crore figure.

How the figure changed to Rs 2.27 crore

On September 8, 2026, Adani Green Energy's Chief Operating Officer Naresh Telgu submitted a notarised affidavit regarding the project cost to the Principal Chief Conservator of Forests, Maharashtra.

The affidavit stated: "While submitting the part IV the cost of the project is considered based on analogous estimation, we considered as INR 56.75 crore, request you to please consider the same as project cost."

On October 12, PCCF Reddy informed Adani Green Energy that his office had accepted the revised project cost of Rs 56.75 crore. He asked the company to immediately deposit 1 percent of this amount, Rs 56.75 lakh, and pay the remaining 3 percent, Rs 1.7075 crore, after the National Board for Wildlife's approval. The company subsequently deposited Rs 56.75 lakh into the Sahyadri Tiger Reserve's bank account.

The revision cut the wildlife deposit from Rs 227 crore to Rs 2.27 crore, a difference of Rs 224.73 crore.

The complaint and the inquiry

On October 30, Rohan Bhate, Honorary Wildlife Warden of Satara district, registered a complaint on the Prime Minister's grievance redressal portal and the Maharashtra government's Aaple Sarkar grievance redressal portal, alleging an "incorrect cost of the project".

On November 6, the Ministry of Environment, Forest and Climate Change directed the state forest department to investigate the matter on priority. The state forest department has initiated a probe.

The cost revision became public on November 13.

What the company says

In its first response, an Adani Group spokesperson had said: "All the Tarali PSP elements are within private land ownership across three revenue villages in Patan taluka and have no Forest land. PSPs do not have any adverse impact on the downstream ecology, environment, forest, or wildlife in the area during operations."

After the matter became public on November 13, the company issued a statement rejecting the allegation that it had sought to revise the project cost downwards to reduce its statutory obligations.

The spokesperson said: "The allegation that the company sought to revise project costs downwards to diminish statutory obligations is completely misleading. The online proposal in the Forest/wildlife portal was solely for site investigation purposes, while SBWL considered total project costs of Rs 5,675 crore."

The company said the Rs 56.75 crore figure covered only site investigation and survey costs, which run to about 1 percent of the total project cost.

The company also said the project sits entirely on private, non-forest land, 3.2 km from the Koyna wildlife sanctuary, outside the notified buffer zone of the Sahyadri Tiger Reserve, and does not affect the tiger corridor or any notified Eco Sensitive Zone. It said the project causes no diversion of protected areas, reserve forest or notified Eco Sensitive Zone.

Why work has been stopped

On November 13, within hours of the matter becoming public, the forest department ordered all work at the Tarali project site to stop immediately. The department said work had commenced without prior approval from the National Board for Wildlife, which it considered mandatory because the project site falls within the deemed Eco-Sensitive Zone of the Sahyadri Tiger Reserve. It sought a detailed written explanation from the company, along with all statutory clearance documents, maps and tree-cutting permissions for the site.

Responding to the order, Adani Green Energy said: "No component of the Tarali Pumped Storage Project falls within any notified Protected Area and no forest land is involved in the project. Further, necessary permissions/NOCs relating to land use and statutory requirements have already been obtained from the competent authorities." It said it had secured Environmental Clearance on February 11, 2025, and Consent to Establish on April 7, 2025, after which construction began, and that its wildlife clearance proposal was pending with the National Board for Wildlife.

Separately, the Maharashtra Pollution Control Board directed a stop to excavation and construction work at Sawarghar village, saying the work was done without its permission and without environmental clearance. The company said these are construction-support facilities, not permanent project components, which "have the requisite statutory clearances".

What happens next

The state forest department's probe, ordered by the Centre, is under way. The National Board for Wildlife is yet to consider the project proposal, and the remaining 3 percent of the revised deposit, Rs 1.7075 crore, is to be paid only after its approval.

Whether the revised project cost of Rs 56.75 crore stands will decide whether the company owes the remaining Rs 224.73 crore of the wildlife deposit. Until the inquiry and the wildlife board's decision are complete, construction at the Tarali site remains halted.

Frequently Asked Questions

What is the dispute over Adani's Tarali project?

Adani Green Energy filed an affidavit cutting the declared cost of its 1,500 MW Tarali pumped storage project from Rs 5,675 crore to Rs 56.75 crore. That cut the wildlife conservation deposit it had to pay from Rs 227 crore to Rs 2.27 crore.

Why is a wildlife deposit linked to the project cost?

The project falls within the deemed Eco-Sensitive Zone of the Koyna Wildlife Sanctuary, part of the Sahyadri Tiger Reserve. Under existing norms, up to 4 percent of a project's cost can be sought as a deposit towards conservation and protection in such a zone.

Has work at the Tarali site stopped?

Yes. The forest department ordered all work to stop on November 13, saying it began without approval from the National Board for Wildlife. The Maharashtra Pollution Control Board separately ordered excavation and construction work at Sawarghar village to stop.

Read More: Explained: Ganga Water Treaty Ends December 12, What Happens Next

Read More: Explained: Jensen Huang Returns as Nvidia CEO, Why His Comeback Faces US Scrutiny

Read More: Explained: Record Profits, Stagnant Pay, Why PM Modi Scolded India Inc

Read More: Explained: Supreme Court Backs BS-VI Only Vehicles for Delhi

Share this story